Project Summary
Scope of work:
Redevelopment of 15-acre site including new Pre-Gate Facility, with HGV driver welfare and parking facilities. Steel framed and modular buildings;
restaurant, showers, restrooms and office.
Contract included:
- 57,000 person hours
- 34,000t of tarmac
- 4 miles of ducting
- 3 miles of white lining
- 1 mile of fencing
- 39 traffic islands
- 300m foul pumping main
- 2,864m3 ready mix concrete
- 87t of steel rebar
- 8 EV chargers
- Cart away 1,600 loads of arisings
Client: DP World Southampton
Location: Southampton Docks
Project Duration: 40 Weeks
Design and Construct Contract
Contract Value: £14.3m